← Back to Project Technician working on the top deck of a cooling-tower cell at the site, beside the water-distribution header and fill packs

Thailand: Eight-Unit Cooling Tower Preventive Maintenance

Synergy Services completed the scope documented below. Measured results are shown only where this page states them.

Annual preventive maintenance across eight cooling-tower units, integrating vibration spectrum analysis, alignment, lubrication and leak correction.

Project at a glance

ItemProject record
CustomerSite identity withheld
LocationThailand
Source basisContracted work order; completed
Publication statusCompleted scope; measured results are shown only where stated

Source-backed scope

  • Perform vibration spectrum analysis before/after maintenance.
  • Inspect bearings, gear condition and backlash.
  • Replace lubricant, align gearbox/drive shaft/motor and adjust fan pitch/tip clearance.
  • Correct identified gearbox oil leaks using gasket sealant and epoxy build-up methods.

Engineering focus

This is a fleet-style PM case rather than a single-cell repair, useful for showing repeatable inspection and condition-monitoring capability.

Project status

Scope completed as documented above. This page describes the contracted work; measured results are shown only where the page states them. Images on this page document the work covered by this scope.