← Back to Project

SCGC Group Cooling Tower Fill Replacement — 5 Plants, 25 Cells

SCGC Group operates petrochemical plants across Rayong and Map Ta Phut.

Between 2021 and 2024, Synergy Services replaced cooling tower fill across 25 cells at five plants: Map Ta Phut Olefins (MOC), Rayong Olefins, Thai Plastic and Chemicals (TPC), Thai Polyethylene (TPE), and Thai MMA (TMMA).

These fill replacements sit within Synergy Services’ price-list contract with the SCGC group, which ran from 2022 to 2025 across seven plants.

At a glance

FieldPublished project record
Client and sitesSCGC Group petrochemical plants in Rayong and Map Ta Phut
Tower type and cellsCooling towers · 25 cells across 5 plants
Design dutyNot published in the project record.
ScopeFill-pack replacement across 5 plants; the related price-list contract covered 7 plants
Products installedTerra TCI-C-19CC, TCI-C-VOF20, and TCI-C-BOF21 film fill
Dates2021–2024 for the published replacement work; price-list contract 2022–2025
Outage per cellNot published in the project record.
Measured resultNot published in the project record.

 

Fill installed by plant

ClientCellsFill modelCompleted
Map Ta Phut Olefins Co., Ltd (MOC)9Terra TCI-C-19CC, Terra TCI-C-VOF202021–2024
Rayong Olefins Co., Ltd8Terra TCI-C-19CC, Terra TCI-C-VOF202021–2024
Thai Plastic and Chemicals (TPC)2Terra TCI-C-19CC2023
Thai Polyethylene Co., Ltd (TPE)3Terra TCI-C-19CC2023
Thai MMA Co., Ltd (TMMA)3Terra TCI-C-BOF212023

 

The problem

What we found

Baseline measurement

Fill selection and why

Execution

Synergy Services completed the published replacement work across five plants and 25 cells between 2021 and 2024.

The related price-list contract ran from 2022 to 2025 and covered seven SCGC Group plants.

What was difficult

Verified result

 

Cooling tower fill replacement at SCGC Group plants in Rayong and Map Ta Phut

 

Terra fill installed at SCGC Group cooling tower cells

 