← Back to Project Cooling-tower fan and drive at the site SDK6 during the mechanical overhaul

Saraburi: Multi-Cell Cooling Tower Mechanical Overhaul

Synergy Services was awarded the scope documented below. This page presents the contracted engagement without claiming completion or measured results unless separate evidence is explicitly stated.

Multi-cell shutdown work combining fan-blade replacement, blade coating, gearbox overhaul, lubricant replacement and laser alignment.

Project at a glance

ItemProject record
CustomerSite identity withheld
LocationSaraburi, Thailand
Source basisAwarded work order
Publication statusAwarded scope; completion and measured results are not asserted

Source-backed scope

  • Replace fan blades on Y81 CT5 and CT6.
  • Coat fan blades on CT4, CT5 and CT6.
  • Overhaul the CT4 gearbox, including a replacement gearbox within the job scope.
  • Replace gearbox oil and perform motor-to-gearbox laser alignment.

Engineering focus

This is a strong multi-cell outage case because it combines different corrective actions across adjacent cells within one shutdown window.

Project status

Synergy Services was awarded this scope. This page describes contracted work; completion and measured results are not claimed unless explicitly supported. Images on this page document the work covered by the awarded scope.