Synergy Services completed the scope documented below. Measured results are shown only where this page states them.
Cooling-tower gearbox removal, workshop overhaul and reinstallation with bearing/oil-seal replacement and vibration checks.
Project at a glance
Item
Project record
Customer
Site identity withheld
Location
Rayong, Thailand
Source basis
Contracted work order; completed
Publication status
Completed scope; measured results are shown only where stated
Source-backed scope
Measure vibration and fan geometry before dismantling.
Remove the gearbox for workshop overhaul.
Dismantle, clean and PT-test the gearbox; replace bearings and oil seals.
Reinstall the overhauled gearbox and conduct post-installation vibration measurement and test run.
Engineering focus
This is a clear end-to-end gearbox service workflow, from baseline measurement through workshop overhaul to field recommissioning.
Project status
Scope completed as documented above. This page describes the contracted work; measured results are shown only where the page states them. Images on this page document the work covered by this scope.