Synergy Services completed the scope documented below. Measured results are shown only where this page states them.
Cooling-tower PM inspection across multiple plant blocks covering drive components, structure, fill, nozzles, drift eliminators, fan geometry and alignment.
Project at a glance
Item
Project record
Customer
Site identity withheld
Location
Rayong, Thailand
Source basis
Contracted work order; completed
Publication status
Completed scope; measured results are shown only where stated
Source-backed scope
Inspect shafts and flexible drive elements.
Inspect internal partitions and cooling-tower structure.
Inspect PVC fill packs, spray nozzles and drift eliminators.
Inspect fan-blade tip clearance/angle and recheck motor-to-gearbox alignment.
Engineering focus
The source lists several block/cell tags but contains a repeated block entry, so this page intentionally avoids publishing a total cell count until the inspection report is reconciled.
Project status
Scope completed as documented above. This page describes the contracted work; measured results are shown only where the page states them. Images on this page document the work covered by this scope.