Five-Plant Cooling Tower Fill Replacement, Rayong

The petrochemical group operates petrochemical plants across Rayong and Map Ta Phut.

Between 2021 and 2024, Synergy Services completed fill replacement work across 25 cells at five petrochemical plants.

These fill replacements sit within Synergy Services’ price-list contract with the petrochemical group, which ran from 2022 to 2025 across seven plants.

At a glance

FieldPublished project record
Client and sitesSite identity withheld
Tower type and cellsCooling towers · 25 cells across 5 plants
Design dutyNot published in the project record.
ScopeFill-pack replacement across 5 plants; the related price-list contract covered 7 plants
Products installedTCI-C-19CC, TCI-C-VOF20, and TCI-C-BOF21 film fill
Dates2021–2024 for the published replacement work; price-list contract 2022–2025
Outage per cellNot published in the project record.
Measured resultNot published in the project record.

 

Fill installed by plant

PlantCellsFill modelCompleted
Plant 19TCI-C-19CC, TCI-C-VOF202021–2024
Plant 28TCI-C-19CC, TCI-C-VOF202021–2024
Plant 32TCI-C-19CC2023
Plant 43TCI-C-19CC2023
Plant 53TCI-C-BOF212023

 

The problem

What we found

Baseline measurement

Fill selection and why

Execution

Synergy Services completed the published replacement work across five petrochemical plants and 25 cells between 2021 and 2024.

The related price-list contract ran from 2022 to 2025 and covered seven plants in the petrochemical group.

What was difficult

Verified result

 

Cooling tower fill replacement at the five petrochemical plants in Rayong and Map Ta Phut

 

Fill installed at the petrochemical group cooling tower cells