Ratchaburi: Drift Eliminator Replacement and Two-Cell Cleaning
June 10, 2026
Synergy Services completed the scope documented below. Measured results are shown only where this page states them.
Supply and installation of TCI-DE-40/120 drift eliminators on one cell combined with cleaning of fill, structure, fan stack, fan blades and basin across two cells.
Project at a glance
Item
Project record
Customer
Site identity withheld
Location
Ratchaburi, Thailand
Source basis
Contracted work order; completed
Publication status
Completed scope; measured results are shown only where stated
Dismantle the existing drift eliminator and install the new system on one cell.
Wash hanging-grid fill from top and bottom across two cells.
Clean drift eliminator, structure, fan stack, fan blades and basin and remove basin sludge.
Engineering focus
The job order specified a 10-week spare-part lead time. This page presents the scope as documented in the job order.
Project status
Scope completed as documented above. This page describes the contracted work; measured results are shown only where the page states them. Images on this page document the work covered by this scope.