Rayong: BAC Evaporative Condenser Supply and Installation

Synergy Services completed the scope documented below. Measured results are shown only where this page states them.

Supply, factory acceptance test and installation of a new stainless-steel BAC Vertex™ evaporative condenser that replaces an existing unit at an industrial gas plant in Rayong, completed in 2026.

Project at a glance

ItemProject record
CustomerSite identity withheld
LocationRayong, Thailand
IndustryIndustrial gas plant
EquipmentBAC Vertex™ evaporative condenser, 304 stainless steel, 1 unit, replacing an existing unit
ManufacturerBAC, at its Dalian, China plant
Year2026
Source basisContracted work order; completed
Publication statusCompleted scope; measured results are shown only where stated

BAC manufactured the unit. Synergy Services supplied it, ran the factory acceptance test (FAT) and installed it.

FAT at BAC Dalian

The factory acceptance test (FAT) took place at BAC’s Dalian plant, where the unit was built. It covered the dimensional and quality-assurance (QA) inspection of the unit. The hero photo above shows the finished three-fan unit in BAC’s yard with its fan guards fitted; below, the inspection group examines the fan side of the unit alongside BAC personnel.

Factory acceptance test group, some in BAC vests, inspecting the fan side of the new unit at BAC’s plant

Removal and installation in Rayong

Synergy Services removed the old unit and installed the new one on the existing platform, using a crane/Hiab lift and scaffolding. The new unit was lifted into place in sections.

A crane lifting a casing section of the new unit at the Rayong plant, with ground crew below
A section of the new unit with three fans hanging from a crane against the sky
A module bearing the BAC logo being landed by crane onto the existing platform, with installers guiding it
A lower section of the unit under crane at the Rayong plant
Installers guiding the fan section of the new unit into place under crane

After the lift, Synergy Services modified the piping to suit the new unit, and carried out a nitrogen (N₂) pressure test and UT/RT leak testing on site. The existing wiring was reconnected to the new motors.

The new BAC Vertex™ evaporative condenser installed on the platform, seen from the walkway beside its fan guard

The Synergy and BAC installation team standing together on the installed unit

Scope split

Synergy ServicesThe customer
Supply of the new BAC unitFoundation and platform
FAT at BAC Dalian, including the dimensional and QA inspectionUtilities
Removal of the old unit and installation of the new one, including the crane or Hiab lift, scaffolding and engineering supportWaste disposal
Piping modification to the new unitFlushing, water quality and passivation before start-up
N₂ pressure test and UT/RT leak testing on siteThe rescue team
Electrical reconnection of the existing wiring to the new motors

Engineering focus

The job order specified a 12-week ex-works lead time. This page presents the whole-unit scope as documented in the job order.

Project status

Scope completed as documented above. This page describes the work Synergy Services carried out; it publishes no capacity, energy or performance figures. Images on this page document the work covered by this scope.