Rayong: BAC Evaporative Condenser Supply and Installation
Synergy Services completed the scope documented below. Measured results are shown only where this page states them.
Supply, factory acceptance test and installation of a new stainless-steel BAC Vertex™ evaporative condenser that replaces an existing unit at an industrial gas plant in Rayong, completed in 2026.
Project at a glance
| Item | Project record |
|---|---|
| Customer | Site identity withheld |
| Location | Rayong, Thailand |
| Industry | Industrial gas plant |
| Equipment | BAC Vertex™ evaporative condenser, 304 stainless steel, 1 unit, replacing an existing unit |
| Manufacturer | BAC, at its Dalian, China plant |
| Year | 2026 |
| Source basis | Contracted work order; completed |
| Publication status | Completed scope; measured results are shown only where stated |
BAC manufactured the unit. Synergy Services supplied it, ran the factory acceptance test (FAT) and installed it.
FAT at BAC Dalian
The factory acceptance test (FAT) took place at BAC’s Dalian plant, where the unit was built. It covered the dimensional and quality-assurance (QA) inspection of the unit. The hero photo above shows the finished three-fan unit in BAC’s yard with its fan guards fitted; below, the inspection group examines the fan side of the unit alongside BAC personnel.

Removal and installation in Rayong
Synergy Services removed the old unit and installed the new one on the existing platform, using a crane/Hiab lift and scaffolding. The new unit was lifted into place in sections.





After the lift, Synergy Services modified the piping to suit the new unit, and carried out a nitrogen (N₂) pressure test and UT/RT leak testing on site. The existing wiring was reconnected to the new motors.


Scope split
| Synergy Services | The customer |
|---|---|
| Supply of the new BAC unit | Foundation and platform |
| FAT at BAC Dalian, including the dimensional and QA inspection | Utilities |
| Removal of the old unit and installation of the new one, including the crane or Hiab lift, scaffolding and engineering support | Waste disposal |
| Piping modification to the new unit | Flushing, water quality and passivation before start-up |
| N₂ pressure test and UT/RT leak testing on site | The rescue team |
| Electrical reconnection of the existing wiring to the new motors |
Engineering focus
The job order specified a 12-week ex-works lead time. This page presents the whole-unit scope as documented in the job order.
Project status
Scope completed as documented above. This page describes the work Synergy Services carried out; it publishes no capacity, energy or performance figures. Images on this page document the work covered by this scope.