Cooling Tower Cell D Fill Replacement and Performance Assessment

Synergy Services replaced spray nozzles, fill packs and drift eliminators on the cooling tower Cell D, then compared thermal performance and airflow before and after the work.

The original manufacturer performance curve was unavailable, so the report did not claim a formal rated tower capability. Instead it used cooling-tower effectiveness as a comparative indicator and recorded the different operating conditions between the two tests.

Measured comparison

ParameterBefore · 17 Feb 2026After · 5 Jun 2026
Water flow2,807.60 m³/h2,248.00 m³/h
Hot water32.90°C34.00°C
Cold water26.70°C29.29°C
Wet bulb25.11°C28.62°C
Cooling effectiveness79.58%87.55%
Airflow326.09 m³/s337.46 m³/s
Fan power102.67 kW102.67 kW

The recorded effectiveness increased by 7.97 percentage points (about 10% relative) and airflow increased while fan power remained unchanged.

Cooling tower work inside Cell D

Important limitation

Water flow, hot-water temperature and ambient wet-bulb conditions were different between tests. The report therefore treats the result as a comparative assessment under the measured conditions, not a strict like-for-like acceptance test.

That limitation is important for credible engineering communication: the project supports a measured improvement under the two test conditions, while a formal design-capability claim would require the manufacturer curve and controlled test conditions.