Chonburi: Cooling Tower Gearbox Replacement

Synergy Services completed the scope documented below. Measured results are shown only where this page states them.

Cooling-tower Cell 1 gearbox replacement with a 60-ton mobile crane, baseline alignment/fan measurements, oil service, recommissioning and vibration checks.

Project at a glance

ItemProject record
CustomerSite identity withheld
LocationChonburi, Thailand
Source basisContracted work order; completed
Publication statusCompleted scope; measured results are shown only where stated

Source-backed scope

  • Record drive-shaft alignment, shaft gaps, blade pitch and tip clearance before dismantling.
  • Remove fan/hub/gearbox using a 60-ton mobile crane and restore the gearbox baseplate/foundation surface.
  • Install the new gearbox, fan/hub and coupling and refill oil/grease.
  • Reset alignment and fan geometry, test run, record vibration and perform post-operation re-torque.

Engineering focus

The scope record is unusually detailed on dismantling, lifting, recommissioning and post-run re-torque, so this public page keeps process detail while omitting customer contacts and commercial data.

Project status

Scope completed as documented above. This page describes the contracted work; measured results are shown only where the page states them. Images on this page document the work covered by this scope.