Chonburi: Cooling Tower Gearbox Replacement
Synergy Services was awarded the scope documented below. This page presents the contracted engagement without claiming completion or measured results unless separate evidence is explicitly stated.
Cooling-tower Cell 1 gearbox replacement with a 60-ton mobile crane, baseline alignment/fan measurements, oil service, recommissioning and vibration checks.
Project at a glance
| Item | Project record |
|---|---|
| Customer | Site identity withheld |
| Location | Chonburi, Thailand |
| Source basis | Awarded work order |
| Publication status | Awarded scope; completion and measured results are not asserted |
Source-backed scope
- Record drive-shaft alignment, shaft gaps, blade pitch and tip clearance before dismantling.
- Remove fan/hub/gearbox using a 60-ton mobile crane and restore the gearbox baseplate/foundation surface.
- Install the new gearbox, fan/hub and coupling and refill oil/grease.
- Reset alignment and fan geometry, test run, record vibration and perform post-operation re-torque.
Engineering focus
The awarded-scope record is unusually detailed on dismantling, lifting, recommissioning and post-run re-torque, so this public page keeps process detail while omitting customer contacts and commercial data.
Project status
Synergy Services was awarded this scope. This page describes contracted work; completion and measured results are not claimed unless explicitly supported. Images on this page document the work covered by the awarded scope.